Reference

Explore our projects across Germany

Nine completed photovoltaic power plants — from projects in rugged terrain to our contribution to the largest solar park in Europe.

01 / 09
Capacity
Panels
Project details
Leipzig Solar Park — realizace 24Energy
Largest in EuropeGround-mounted

Leipzig Solar Park

68 MW
Our share of 650 MW
128 301
Panels out of 1,226,415

The solar power plant near Leipzig is part of the largest solar power plant in Europe and was our first project of this scale. Out of the total 650 MW, we delivered a 68 MW portion.

The construction placed exceptional emphasis on occupational safety, precise coordination, and compliance with strict technical and organizational standards.

Request a similar project
Bad Königshofen — realizace 24Energy
Internal recordGround-mounted

Bad Königshofen

20 MW
Installed capacity
36 390
Number of panels

A large-scale project in which our team achieved exceptional performance: 34 installers installed 9,530 panels in two days, setting a new internal record.

The result demonstrates efficiency, precise organization, and seamless teamwork.

Request a similar project
Adelsheim — realizace 24Energy
Ground-mounted

Adelsheim

15 MW
Installed capacity
25 218
Number of panels

The 15 MW photovoltaic power plant, with a total of 25,218 installed modules on an MKG Göbel mounting system, was among the most logistically demanding projects.

The construction was divided into several separate sections, one of which was located on very steep terrain. Adverse weather, coordination of material deliveries, and the large number of workers required precise planning to ensure the power plant was completed according to the specified requirements.

Request a similar project
Flachslanden 2 — realizace 24Energy
Steep slopeRugged terrain

Flachslanden 2

12 MW
Installed capacity
27 586
Number of panels

One of the most technically demanding projects. The construction took place on a steep slope on a hill, in exceptionally rugged terrain.

The proximity of a protected natural area was an additional challenge, requiring enhanced environmental measures.

Request a similar project
Ganheim — realizace 24Energy
Ground-mounted

Ganheim

10 MW
Installed capacity
15 885
Number of panels

The 10 MW photovoltaic power plant with 15,885 installed modules on an MKG Göbel mounting system was among the most technically demanding projects.

The construction site was located in the immediate vicinity of a German motorway and on rugged, sloping terrain. The challenging conditions complicated both the installation of the mounting structures and the panels, but thanks to an experienced team and precise coordination, the project was completed to the required quality and on schedule.

Request a similar project
Ansbach Eyb — realizace 24Energy
Completed in 4 weeksGround-mounted

Ansbach Eyb

9,18 MW
Installed capacity
21 216
Number of panels

The construction was completed in just four weeks, highlighting the efficiency of the project delivery and the team's coordination.

The project was notable for the deployment of a new mounting system.

Request a similar project
Hausen bei Würzburg — realizace 24Energy
Completed in one monthGround-mounted

Hausen bei Würzburg

8 MW
Installed capacity
18 390
Number of panels

A ground-mounted power plant built in record time — the entire project took just one month.

An example of efficient planning and precise work organization.

Request a similar project
Markt Bibart — realizace 24Energy
Agrivoltaics

Markt Bibart

7 MW
Installed capacity
16 088
Number of panels

The project's uniqueness lies in the dual use of the land. It is an agrivoltaic project where energy production is combined with agriculture — pigs will graze beneath the panels.

Request a similar project
Olching — realizace 24Energy
Ground-mounted

Olching

7 MW
Installed capacity
10 320
Number of panels

The 7 MW photovoltaic power plant with 10,320 installed modules on an MKG Göbel mounting system stands out for its unusual location in the immediate vicinity of a family home.

In addition to installing the mounting structures and panels, the project included complete AC and DC installations, construction of the transformer station area, and installation of cable routes. Routing trenches between the rows of panels required careful planning, coordination, and compliance with high safety standards.

Request a similar project
Herrnberchtheim — realizace 24Energy
Agrivoltaics3 m mounting structure

Herrnberchtheim

2,98 MW
Installed capacity
6 850
Number of panels

The first project of this type that we delivered. The power plant was built more than three metres above ground, placing increased demands on installation procedures and occupational safety.

The challenging logistics of material handling were a significant challenge.

Request a similar project
Wolferstadt — realizace 24Energy
A-shaped mounting structureRugged terrain

Wolferstadt

2,3 MW
Installed capacity
5 287
Number of panels

A project carried out in very rugged terrain, placing increased demands on installation precision and construction organization.

The power plant stands around three metres above ground, with the panel rows arranged in an “A” shape — like a pitched roof.

Request a similar project
Prummern — realizace 24Energy
Ground-mounted

Prummern

1 MW
Installed capacity
1 626
Number of panels

We delivered this smaller but technologically interesting 1 MW project in Prummern as an agrivoltaic installation. For the installation of 1,626 modules, we used an MKG Göbel mounting system and the modern 2.0 assembly process.

We handled the project in full — from installing the mounting structures and panels to the AC and DC systems. The project also included pulling DC cables through a trench nearly 400 metres long, effectively connecting clean energy production with the use of agricultural land.

Request a similar project
Wasgau Kaiserslautern — realizace 24Energy
Ground-mounted

Wasgau Kaiserslautern

1 MW
Installed capacity
1 067
Number of panels

The 1 MW photovoltaic power plant with 1,067 installed modules on an MKG Göbel mounting system was built at a Wasgau industrial site.

Although this was a smaller project, we handled the complete delivery, including mounting structure installation, AC and DC installations, cable routes, and earthworks. Thanks to effective organization and an experienced team, the construction was completed quickly, efficiently, and according to schedule.

Request a similar project